For KVIS Pardubice a.s., we participated in the project to replace the elevated water tank in the municipality of Vysoké Chvojno, where we provided the electrical and I&C components. The project began with the preparation of the detailed design documentation and continued with the implementation itself in two consecutive phases.

In the first phase in 2024, we installed the grounding system into the foundations of the new water tank. The second part took place in September 2025, when the construction of the new water tank and the installation of key technological elements followed.

As part of the delivery, we implemented a modern measurement and control (I&C) system. We equipped the water tank with tensometric level measurement, a maximum level sensor, and an inclinometer for monitoring the object's tilt. This also included free chlorine and pH measurement from Endress+Hauser. In the electrical part, we supplied object lighting and heating cables for the inlet and outlet pipelines.

The project also included modifications to the RM2 distribution board in the water tank's switchgear, the addition of a control system including backup batteries, and software and visualization adjustments. We collaborated with GDF on this part. A security system was also installed throughout the entire facility, in cooperation with SITEL.

After completing the installations, we carried out the necessary tests, arranged for technical inspections and certifications, and commissioned the technology.

Project Benefits
The new elevated water tank provides greater storage capacity, modern technological infrastructure, and higher operational reliability. The I&C system, water quality measurement, security, and electrical system modifications help ensure safe and stable water supply operations in the municipalities of Vysoké Chvojno and Habřina.

No items found.

NÁVRH TECHNICKÉHO ŘEŠENÍ

Design activity

PROJECT MANAGEMENT

Tangible supplies

Manufacture of distribution boards

SW CREATION

ASSEMBLY ACTIVITIES

COMMISSIONING

REVISION ACTIVITIES

SERVIS 24/7

Systémy řízení

Mar

Elektro

This seriously

worth noting
You have given us your trust here

When we succeed, we like to brag

We have successfully implemented over 6,000 projects in the energy sector, chemical industry, water management and other industries.

Location

Blog title heading will go here

Vysoké Chvojno

Vysoké Chvojno Water Tank – Electrical and I&C

Production plant Častolovice

Expansion of production - a new line for the production of mineral wool

Prunerov Power Plant

Camera system, Severní lom - EPRII

Prunéřov Power Plant

Reconstruction of the control room DPD, North quarry - EPRII

Kněžice Biogas Station

Replacement of the control system — BPS Kněžice

Žihle Biogas Station

Replacement of the control system — BPS Žihle

Projekt číslo 0380000695 byl financován Evropskou unií
„Podpora kreativity ve společnosti SUMO s.r.o.“ – Marketingová strategie a webdesign firemních webových stránek.